How long does each conversion type take to build?
Build time scales with how much the roof structure changes — Velux conversions are fastest since the roofline stays the same, while mansards take longest because most of the rear roof is rebuilt.
The build programme is driven mainly by how much the roof's external shape and structure change. A Velux or rooflight conversion, which alters no external structure, is the fastest at roughly 4–6 weeks. A standard rear dormer, involving a new structural box on the roof, typically takes 8–10 weeks. Hip-to-gable and L-shaped dormer conversions, which rebuild more of the roof or add a second dormer, generally run 10–14 weeks. A mansard, effectively a partial rebuild of the rear roof, is the longest at 12–16 weeks.